| Owner: |
Atlantic Richfield Company |
| Project Budget: |
$10 million |
| Service Performed: |
Construction Management, Safety Monitoring, Quality Control, Field Layout |
Anderson was retained by the PRP to provide project management and construction oversight for the remedial action at the Copperton tailings site near Salt Lake City, Utah.
The impoundment design included the creation of five earthen cells, (over an existing tailings facility), with a sophisticated cap to prevent infiltration and provide a surface for a sustainable vegetative cover. Work included design, management and oversight for placement of impacted soils from an associated residential yard remediation project, construction of the composite liner system (clayment, synthetic liner, gravel and topsoil), construction of the surface and below surface drainage control system, installation of rip rap slope protection and revegetation of all disturbed areas.
|
|
Last Updated on Wednesday, 10 September 2008 10:53 |